Deutsch English Francais Kitselection Building log Panel Lighting Engine Gadgets
Up
Documents
January 2007
February 2007
March 2007
April 2007
May 2007
June 2007
July 2007
August 2007
September 2007
October 2007
November 2007
December 2007
January 2008
February 2008
March 2008
April 2008
May 2008
June 2008
July 2008
August 2008
September 2008
October 2008
November 2008
December 2008
January 2009
February 2009
March 2009
April 2009
May 2009
June 2009
July 2009
August 2009
September 2009
October 2009
November 2009
December 2009
January 2010
February 2010
March 2010
April 2010
May 2010
June 2010
July 2010
August 2010
September 2010
October 2010
November 2010
December 2010
January 2011
February 2011
March 2011
April 2011
May 2011
June 2011
July 2011
August 2011
September 2011
October 2011
December 2011
January 2012

December 2010

05.12.2010:  I am back from my holidays, and on my project again. Next week I will do the first 25 hrs maintenance, in parallel I can now finish all the paperwork for the final certification. I have tried over the last few weeks to find a noise certificate from a SportCruiser with the same engine / propeller combination, but without success. This means that I will have to make the noise measurement next spring during one of the EAS measuring campaigns.   

 

12.12.2010:  Unfortunately I did not consider my job in my plan to do the first 25 hrs maintenance. Since I returned from my holidays I have already been back to Australia for a week, and I am right now sitting in the plane to go there again. My plan now is to do it on the 20th December. I will also finish all the paperwork over the Christmas Holidays.

 

21.12.2010:  Today I finally went to the airport to do the first 25 hrs maintenance ceck on my SportCruiser. Before I could start, however, I updated the software of all the Dynons on our club's SportCruiser HB-WYC. It still had version 5.1.1, and the current one is 5.4. Some pilots were reporting communication errors between the different Dynon units during flight, so let's see whether this cures the problem. I also created a locked setup on the D-120 to prevent the club's members from reconfiguring it to their individual tastes. I will do the same on the D-100, but our OPS guys first have to tell me how they want it to be configured. The whole story took me a few hours, so I could only start working on my plane in the afternoon. 

First Silvan told me to check the Rotax website for updates of the maintenance manual, and indeed there is a new edition 2, revision 0, dated July 1st 2010. Contrary to the previous edition 1, Rev. 0, the 25 hours maintenance is now identical to a full 100 hrs check. That meant that I of course did not manage to finish everything in the remaining few hours of the afternoon, so I will be back tomorrow.

.

22.12.2010:  Even though it was not planned I spent a few hours this morning finishing the 25 hrs maintenance check. Everything went well and also looked. The oil filter, oil reservoir and magnetic plug show no significant traces of metallic chips, and also the exhaust does not show any cracks. A number of SportCruiser builders had cracks in their exhaust, but mine seems not to be from the affected lot. As it was not planned that I return today I could not finish all the paperwork, but I did do the post maintenance engine test run, which went perfectly well. I will return during the Christmas Holiday to finish all the paperwork. 

 

<< Previous    Next >>

Zugriffszähler

© 2006-2010 Bernhard Stamm       last update: 09.01.2011